How many CQM Documentations are there?

CQM Documentations required as part of the CQM Framework to ensure an integrated quality management system are based on workflow and information knowledge management requirements.

The number of these Documentations might seem overwhelming and a waste of time for top Quality Managers and Quality Directors. However, the CQM Methodology is a robust system where components are preserved but methods are customized as Lean as possible to the need and requirements of specific organizations and their Construction Projects.

CQM-Documentations-per-PMBoK-and-CMAA-web

Best Practice for CQM Documentations

CQM required Documentations are essential to the success of the CQM Program, therefore they cannot be deleted or ignored. However, depending on the size of the organization and construction project, many of these Documentations could be grouped in Reports, Meeting Minutes and Email Communications.

For example, a Quality Preparatory Meeting is necessary to be documented, but not all discussions need to be recorded. Since much of the discussions are confirming previous Project Management Planning, the Quality Preparatory Meeting Minutes will cover Meeting information on Time and Location, Attendance, and major issues and conflicts that were discussed and resolved. The Quality Preparatory Meeting is not intended to change any contract requirement, therefore any newly discovered issues must be sent back to the Change Process as a new RFI and receive formal approvals.

CQM Documentations

As mentioned before, CQM Methodology is based on PMBoK Framework with adjustments and improvements considering Project Management Professionalism and Business Administration Best Practices. In addition, CQM Methodology will include the CMAA CQM Documentation recommendation and applies the LEAN Construction Best Practices to Quality Manager’s role for each meeting and document review and approval.

CQM Documentations that are part of an Integrated Quality Management for a Construction Project Management Professional quality performance is listed below. These documents are prepared by various members of the Quality Management Team i.e. Project Manager, Project Superintendent and Project Engineer and it is recommended that a Quality Manager dedicated to the Project participates in the development of these documents or at least have access to them for better CQM Implementation. At a minimum, items that are highlighted with bold lettering should be assigned to the Quality Manager:

Pre-Construction Documentations

  1. Stakeholder Registry
  2. Pre-Qualification Review Forms
  3. Supply Chain Scorecard Reports
  4. Assumption Log & Change Log
  5. Project Life Cycle Description
  6. Sustainability & LEED Requirements
  7. Development Approach & Integrated Project Delivery
  8. Contract Specifications & Requirements
  9. Contract Drawings
  10. Contract Documents
  11. Project Owner Milestones
  12. Risk Management Plan
  13. Dispute Avoidance and Resolution
  14. Risk Registry & Updates
  15. LEAN Project Management Plan
  16. Communication Plan
  17. Cost Analysis & Project Feasibility Studies
  18. Value Engineering Reports & Constructability Reviews
  19. Work Breakdown Structure (WBS)
  20. Definable Features of Work List
  21. Basis of Estimates & Detail Cost Breakdown (DCB)
  22. Resource Assignments & Project Team Assignments
  23. Project Calendar & Duration Estimates
  24. Schedule of Value (SOV) & Cost Forecasts
  25. Project Charter & Team Charters
  26. Pre-Bid Conference & Walkthrough Agenda
  27. Request for Information Log & Requirement Traceability Matrix
  28. Permits, Insurance, Labor Affidavits, and Bonds
  29. Letter of Intent & Notice to Proceed
  30. Kick-off Meeting Agenda & Meeting Minutes

Construction Documentations

  1. Stakeholder Engagement Plan
  2. Risk Management Plan
  3. Documentation of Existing Conditions
  4. Risk Report
  5. Scope Management Plan
  6. Scope Baseline & Requirements Traceability Matrix
  7. Submittal Register, Transmittal Form, and Log
  8. Schedule Management Plan
  9. Schedule Baseline & Construction Schedule
  10. Cost Management Plan
  11. Cost Baseline & Construction Budget
  12. Cash Flow & Contingency Plans
  13. Progress Payment & Pay Applications
  14. Earned Value Management
  15. Performance Measurement Baseline
  16. Status Updates and Progress Reports
  17. Resource Management Plan
  18. Resource Breakdown Structure (RBS) & Calendar
  19. Procurement Plan & Supply Chain Management (SCM)
  20. SCM Solicitation & Information to Bidders
  21. Bid Opening and Evaluation
  22. Buy-outs and Trade-off Value Analysis
  23. SCM Notice to Proceed
  24. Pre-Construction Conference & SCM Kickoff meeting
  25. SCM Permits, Insurance, Labor Affidavits, and Bonds
  26. Advance Work Packages & Installation Work Packages
  27. Construction Coordination and Kick-off Meeting Minutes
  28. Pull Planning & LEAN Best Planner Scheduling
  29. Master Schedule, Six-Week, Three-Week Schedules
  30. BIM Coordination Meeting Minutes
  31. BIM Conflicts and Clash Reports
  32. Requests for Information and Log
  33. Corrective Actions & Punchlists
  34. Change & Configuration Management Plan
  35. Claims Mitigation and Evaluation
  36. LEAN A3 Problem Solving Tracking & Value Stream Mapping
  37. LEED Quality & Environmental Management Manual
  38. Site-Specific Quality Plan & Quality Control Checklists
  39. Health, Safety, Security, Environment HSSE Manual & Plan
  40. Safety and Quality Orientation and Onboarding Sign-in Sheets
  41. Daily safety inspections & Activity Hazard Analysis (AHA)
  42. Inspection, Testing & Evaluation Documents
  43. Quality Metrics & Control Measures
  44. Quality Performance Areas KPA & Indicator Metrics KPIs
  45. Quality Phase Preparatory Meeting Minutes & Sign-in Sheets
  46. Quality Observation Photos & Reports
  47. Deficiency and Rework Items List
  48. Quality Incident Reports
  49. Quality Non-Conformance Report
  50. Quality Activity and Audit Visits Log
  51. Plan of Day Plan & Kaizen Events
  52. Daily Field Reports & Daily Resource Report
  53. SCM Production Reports & Inventory
  54. Long Lead Material & Delivery Dates
  55. Inventory & Production Site Visit Reports
  56. Update Documents & Record Drawings
  57. Pre-start Tests and Commissioning Meetings Minutes
  58. Punchlist Walkthrough and IWP Closeout Workshops
  59. Training and Handover Meetings
  60. Substantial Completion

Post Construction Documentations

  1. Close-out Procedures
  2. Kaizen and Daily Continous Improvement Reports
  3. Updated Issue Log & Lessons Learned
  4. Maintenance and Operation Manuals
  5. Spare Parts & Warranties
  6. Commissioning and Handover
  7. Claims Resolutions
  8. Final Permits and Certificate of Occupancy
  9. Lessons Learned Collection and Knowledge Management
  10. QMS Review and Updates
  11. Contractor Closeout
  12. Final Acceptance & Final Payment
  13. Project Closing Celebration

CQM.US Consultants

Overwhelmed by the amount of CQM Documentation Requirements? Ask a CQM.US Expert how a CQM Implementation plan could be customized to your organization or project’s need to gain the most value of the CQM Methodology and Framework.

YouTube player